Start with the exact entity and project
In New Cairo and the New Administrative Capital, a buyer may hear a group name, a project brand, a sales company name, and a different legal entity on the proposed contract. Write down each name and establish which entity is actually offering the unit, which entity signs, and what authority it has to do so. Ask for the documents supporting those relationships rather than assuming that similar branding means identical responsibility.
Keep the review project-specific. A developer’s completed work elsewhere can be useful context, but it does not prove the title, approvals, construction status, delivery terms, or service arrangements for the particular project under consideration. Match every claim to the relevant project, phase, building, or unit.
Build an evidence file
Ask for the current documents that describe land or allocation rights, the project’s relevant approvals, the unit’s identifying details, the proposed contract, and the payment schedule. The precise documents and their legal effect depend on the project and transaction; have an Egyptian real-estate lawyer review them and confirm any required checks with the competent authority. Keep copies with dates and the name of the source.
For construction and delivery, distinguish dated site evidence from a projected timetable. Ask what the contract says about the delivery date, permitted extensions, completion standard, handover process, and remedies or obligations if the schedule changes. A presentation, progress photograph, or salesperson’s statement can help form questions, but should not replace binding documents.
Test the commercial terms
Compare the complete payment schedule rather than one headline instalment. Include deposits, instalments, delivery payments, maintenance or service amounts, finishing, utility connections, and any transfer or assignment conditions that apply. Ask for the current written schedule and identify whether amounts can change under the draft contract.
Review cancellation, delay, assignment, handover, and dispute clauses with qualified counsel. Ask which statements are contractual, which are estimates, and which depend on future decisions or third parties. If an answer is not documented, list it as unresolved rather than converting it into an assumption.
Use a simple verification record
Create a comparison sheet with four columns: claim, source document, verification status, and follow-up owner. This makes gaps visible when comparing projects across New Cairo and the capital, especially where marketing materials use similar language for different obligations. Keep “not supplied” distinct from “confirmed”; the distinction matters to a decision.
A developer review is not a prediction of project performance. It is a structured way to understand the legal and commercial evidence available at a particular time. Recheck time-sensitive information before signing and obtain independent legal review for the actual transaction documents.